Project Overview

The large-scale roof timber structure project covers about 112,800 square meters, serving residential construction with standardized detailing and prefabricated construction.

Shanghai Junzhi undertook the architectural design and construction, realizing the large-volume roof system through component zoning, standardized joints, and on-site organization.

Project name

Hebei Huailai Shanggu Shuijun Roof Project

Project location

Xiaonanxinbao Town, Huailai County, Hebei Province

Building area

112,800 square meters

Architectural Design

Shanghai Junzhi Architectural Technology Co., Ltd.

Wood Structure Construction

Shanghai Junzhi Architectural Technology Co., Ltd.

Construction cycle

May 2017 – September 2018

Project Archives

Project Name: Shanggu Shuijun, Huailai, Hebei

Geographic Location: South Side of Guanting Reservoir, Donghuayuan Exit of Jingzang Expressway, Huailai, Hebei

Building area: 103,000 square meters

Design Time:2015.10

Completion time:2018.9

Client : Hebei Xuancheng Real Estate Development Co., Ltd.

Responsibilities : Schematic Design, Timber Structure Detailing


Preface:

At present, the prefabrication rate requirements for housing construction are becoming increasingly higher. Prefabricated timber structure construction is one of the directions that the Ministry of Construction of China is vigorously promoting. Among Junzhi's projects, there are also projects of this type that pursue prefabrication rate indicators—the Huailai Timber Roof Project.Building a light wood dimension lumber truss structure timber roof brings, in addition to the benefit of meeting the prefabrication rate standard, three other major advantages.


I. Cost Reduction

The wooden roof was processed and built in the factory according to the drawings, and after being transported to the site,“Construction”The time is the time required for hoisting plus the time for roof surface construction. The on-site construction time of the timber roof is basically the same as the time required for formwork of a concrete roof.


II. Seismic Enhancement

This is all thanks to the fact that a timber roof weighs far less than a concrete roof; once the overall load is reduced, the overall structure is fundamentally optimized. Using a timber roof allows fewer building materials and less on-site construction time to achieve a house with a more stable structure and better seismic performance.


III. Construction Period

Due to the factory prefabrication of the timber roof and dry on-site construction, the entry time for landscape construction can also be advanced. Therefore, the overall on-site construction completion time of all disciplines can be advanced as a whole.Four model buildings come with timber roofs1100Taking the square-meter roof construction project as an example, below zero10Under the condition of degrees, construction before the Lunar New Year15days, crossing the Lunar New Year. Construction after the holiday20days, the actual construction time35days. The overall construction schedule was ensured.In addition, considering the prefabrication rate indicator mentioned earlier, for a two-story house, simply constructing the roof can reach the prefabrication rate ratio required by the current national stage. If some projects require a higher prefabrication rate indicator, for timber structures, as long as both the second floor and the roof of the house are built with timber structure, a higher prefabrication rate can be easily achieved. In the later phase of the Huailai project in the future, as the portion using timber structure increases, these advantages will be reflected even more clearly.

Timber Construction Wisdom